IT Exam,IT Certification,braindump,original questions, question pool,document, braindump, test questions, test question, dumps, test answers, cert24.com, preparation, pdf, certification questions, answers Certification, certification test, practice test, exam dumps, certification training, answers real questions
PMI-002 Certified Associate in Project Management (CAPM) Certification We believe in helping our customers achieve their goals. For this reason, we take great care while preparing our Questions and Answers , Core Administration. Our practice tests Administration are prepared with the help of highly professional people from the industry, so we benefit from their vast experience and knowledge.
www.cert24.com,test dumps, practice test, pdf PMI PMI-002 cert24
QUESTION NO: 1
A contract cannot contain _____________.
A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above
Answer: A
Explanation:
A contract cannot contain illegal activities. A contract can contain other options available.
QUESTION NO: 2
Which one of the following comes first in the project plan?
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Answer: A
Explanation:
Scope statement comes first in the project plan. Scope statement is the written statement of project. It contains: Project objectives, Project justification, Project deliverables
QUESTION NO: 3
You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn’t have the manufacturing capability. This is an example of which selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
Answer: B
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the project.
QUESTION NO: 4
______________ provides details about how the project scope may be changed.
A. Control Scope system
B. VeiirV Scope
C. Scope Charter
D. Scope Management plan
Answer: D