1. A system requires 100% decision coverage at component testing for all

modules. The following module has been tested with a single test case.

The test case follows the path A, B, D, E, F, G. What level of decision

coverage has been achieved?

A. 100%

B. 50%

C. 75%

D. 90%

Answer: B

ISEB-SWT2 ISEB-SWT2 ISEB-SWT2 www.cert24.com

2.During which activity of the Fundamental Test Process test process do

you review the test basis?

A. Evaluating exit criteria and reporting.

B. Test implementation and execution

C. Test analysis and design

D. Test planning and control

Answer: C

ISEB-SWT2 ISEB-SWT2 ISEB-SWT2 www.cert24.com

3.Which of the following statements are true in relation to component

testing?

a. Stubs may be used.

b. May cover resource behaviour (e.g. memory leaks).

c. Tests the interactions between software components.

d. Defects are typically fixed without formally managing these defects.

A. a, c and d

B. a, b and d

C. b, c and d

D. a, b and c

Answer: B