QUESTION 1

Which of the following are process groups in the project life cycle? (Select THREE).

A. Accepting

B. Mitigating

C. Avoiding

D. Initiating

E. Closing

F. Planning

Answer: DEF

PK0-003 PK0-003 PK0-003 www.cert24.com

QUESTION 2

A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?

A. Storming

B. Performing

C. Conforming

D. Forming

Answer: B

PK0-003 PK0-003 PK0-003 www.cert24.com

QUESTION 3

A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?

A. Work Breakdown Structure (WBS)

B. Cost management plan

C. Approved project charter

D. Project scope document

Answer: B

PK0-003 PK0-003 PK0-003 www.cert24.com

QUESTION 4

The project charter is an output of which of the following project phases?

A. Initiation

B. Planning

C. Execution

D. Closing

Answer: A

PK0-003 PK0-003 PK0-003 www.cert24.com

QUESTION 5

All of the following are considered part of the risk management plan EXCEPT the risk:

A. register.

B. matrix.

C. assessment.

D. baseline.

Answer: D