If you want to make a big progress in shortest time and you want to have the achievement within minimum effort,I recommend that you use cert24.com C_TSCM42_64 exam.We believe in helping our customers achieve their goals,because of the highly dedicated and expert team that we have and because of our past performance.
C_TSCM42_64 simulates the actual testing environment which you can focus on various sections of the Exam.Time is the most important element for our customers so we keep that in mind while preparing our product and Our experts come from different parts of the Industry and are most experienced and qualified to have the opportunity to write the exam practice test for us. the exam engine which
helps you a lot in your preparation of exam ,so you can benifit a lot from our product.
Totally hassle free! All you need to do is contact the Customer Support and request for the exam you like. You will be required to scan a copy of your failed exam and mail it to us so you are provided access to another certification test immediately. Your success is insured by the cert24.com Guarantee!
cert24.com is very confident on their C_TSCM42_64exam practice test that it will give you 100% guaranteed success.Give it a thought! You have nothing to lose in it.so with the guide of our product, you will pass the exam at your first try!
Our Exam C_TSCM42_64 Preparation Material provides you everything you will need to take your Exam. The C_TSCM42_64 Exam details are researched and produced by Professional Certification Experts who are constantly using industry experience to produce precise, and logical. You may get questions from different web sites or books, but logic is the key. Our Product will help you pass test in your first try, and also save your valuable time.
QUESTION NO: 1
In production order processing, for which of the following objects can you enter a confirmation? (Choose three.)
A. Work Center
B. Individual Capacity
C. Order
D. Operation / Suboperation
E. Trigger Point
Answer: B,C,D
QUESTION NO: 2
Which one of the following scheduling types cannot be assigned as default to an order type (production order)?
A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward
Answer: A
QUESTION NO:3
In your enterprise, a planning strategy is used in SAP ECC that enables joint planning of all MRP scheduled assemblies for a finished product to trigger procurement of these assemblies. It is important to ensure that the finished product is only produced when there is a customer order present. When a customer order is received, production of the finished product should be triggered in the form of make-to-order planning and production.
Which planning strategy covers this scenario?
A. Planning with make-to-stock (strategy 10)
B. Planning at the assembly level (strategy 70)
C. Planning with final assembly (strategy 40)
D. Planning without final assembly (strategy 50)
Answer: D
QUESTION NO: 4
An enterprise based in the USA produces an end product that is used with the unit of measure “pound” (LB). The material is now to be marketed in the EU. A prerequisite for this is that the material can be sold with the unit kilogram (KG).
Which of the following solutions does SAP ECC offer?
A. In the basic data customizing, you create a unit of measure group that converts pounds to kilograms. You then assign this to the material master on basic data view 1.
B. You create a new material with a reference to the original material and assign the metric unit of measure to the new material master.
C. In the material master, you create a conversion factor for converting pounds to kilograms on basic data view 1.
D. There is no need to take any action. There is a general conversion in the central customizing of units of measurements, so that automatic conversion of pounds to kilograms takes place.
Answer: D
QUESTION NO:5
Which of the following functions are available in the SAP ECC system for leveling overloads in individual work centers with the capacity planning tools? (Choose three.)
A. Midpoint scheduling
B. Batch size optimization
C. Lot size optimization
D. Setup time reduction
E. Finite capacity scheduling
Answer: A,D,E