As we all know,many people think that it is difficult to pass the C_TSCM42_66 exam,In fact, there are many ways to help you make up for your lack of knowledge, and pass the IT certification exams in the same. Perhaps you would spend less time and effort than the people who grasp fairly comprehensive expertise.
If you want to participate in the IT industry’s important SAP C_TSCM42_66 examination, it is necessary to select cert24.com website, because our website is a professional website.our senior experts have developed exercises and answers about SAP certification exam with their knowledge and experience, which have almost similarity with the real exam. I believe that you will be very confident of our products. If you choose to use cert24.com‘s products, Through C_TSCM42_66 examination certification, you will be get a better guarantee. In your career, at least in the IT industry, your skills and knowledge will get international recognition and acceptance.
There is no reason to waste your time on a test. you should use the time to do significant thing. Therefore, hurry to visit cert24.com. to know more details. Miss the opportunity, you will regret it.With our products, you will be brimming with confidence, fully to do the exam preparation.choose our product immediately and success is not far away for you. And soon you can get SAP certification C_TSCM42_66 exam certificate.
QUESTION NO: 1
You want to use the function “Read PP master data” in the production order.
However, while calling the function you receive an error message.
What could be the reason?
A. The material availability check has been performed.
B. Goods movements have been posted.
C. The production order has been released.
D. Order papers have been printed.
Answer: B
QUESTION NO: 2
Which objects can affect the calculation of capacity requirements for an operation? (Choose three)
A. Standard values (routing)
B. In-house production time (material master)
C. Transport time (routing)
D. Formulas (work center)
E. Operation control key (routing)
Answer: A,D,E
QUESTION NO: 3
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type.
What does a firming type define? (Choose two)
A. Handling existing procurement proposals outside the planning time fence.
B. Handling existing procurement proposals within a planning time fence.
C. Handling new requirements within the planning time fence.
D. Handling new procurement proposals that need to be created due to new requirements within the planning time fence.
Answer: B,D
QUESTION NO: 4
Which of the following scheduling types can only be used in capacity planning?
A. Midpoint
B. Forward
C. Only capacity requirements
D. Backward
Answer: A
QUESTION NO: 5
Which types of objects can be changed with Engineering Change Management (ECM)? (Choose three)
A. Task list
B. Work center
C. Production version
D. Bill of material
E. Material master
Answer: A,D,E