IT Certification,braindumps,original questions PRINCE2

IT Certification,braindumps,original questions PRINCE2

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

Exam Number/Code : PRINCE2

Exam Name : PRINCE2 Foundation

Version : Demo

QUESTION 1

In what product is used to define the information that justifies the setting up,

continuation or termination of the project?

A. Project Initiation Document

B. Business Case

C. End Stage Approval

D. Project Brief

Answer: B

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

QUESTION 2

Which product keeps track of Requests For Change?

A. Request Log

B. Daily Log

C. Quality Log

D. Issue Log

Answer: D

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

QUESTION 3

What provision in Planning can be made for implementing Requests for Change?

A. Project and stage tolerances

B. Contingency plans

C. A Change Budget

D. Adding a contingency margin to estimates

Answer: C

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

QUESTION 4

FilL in the missing phrase from” a project is a management environment that is created for the purpose of delivering one or more business products according to……”

A. TheCustomer’sNeds

B. An Agreed Contract

C. The Project Plan

D. A specified Business Case

Answer: D

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

QUESTION 5

In what sequence would the (a) Project Initiation Document, (b) the Project Mandate and (c) the Project Brief appear in a project?

A. a, b, c

B. b, c, a

C. c, a, b

D. c, b, a

Answer: B

PRINCE2 PRINCE2 PRINCE2 www.cert24.com

Comments are closed.