JK0-017 exam study guide

JK0-017 exam study guide

  • Code:JK0-017
  • Click Here: more information
  • Exam Demo:
  • Q1
    Which of the following are process groups in the project life cycle? (Select Three).
    A. Accepting
    B. Mitigating
    C. Avoiding
    D. Initiating
    E. Closing
    F. Planning
    Answer: D,E,F
    Q2
    A project team is comfortable working as a group and has accepted all the project ground rules. They support each other to reach the project goals. Which of the following stages of team development is the project team demonstrating?
    A. Storming
    B. Performing
    C. Conforming
    D. Forming
    Answer: B
    Q3
    A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
    A. Work Breakdown Structure (WBS)
    B. Cost management plan
    C. Approved project charter
    D. Project scope document
    Answer: B
    Q4
    The project charter is an output of which of the following project phases?
    A. Initiation
    B. Planning
    C. Execution
    D. Closing
    Answer: A
    Q5
    All of the following are considered part of the risk management plan EXCEPT the risk:
    A. register.
    B. matrix.
    C. assessment.
    D. baseline.
    Answer: D